由能源部杭州机械设计研究所设计、夹江水工厂制度的漫湾电站无塔低架20t平移式缆机于1988年12月7日进行了试车。载重25t的静态和动态试车、超载试车均一次成功、各项指标达到设计要求。小车运行速度最高达480m/min,重载上升速度120m/min,重载下降速度160m/min,大车平移速度13m/min。由于设计、制造和施工单位现场工作人员的密切配合,在主索过江后40天即完成重载试车,创国内缆机安装调试工期最短记录。
Design by the Department of Energy, Hangzhou Mechanical Design, Jiajiang water plant system Manwan low tower 20t tower crane cable transfer on December 7, 1988 for testing. Load 25t static and dynamic test run, over load test were a success, the indicators meet the design requirements. Car running speed of up to 480m / min, heavy lifting speed of 120m / min, heavy falling speed of 160m / min, trolley speed of 13m / min. Due to the close coordination of the design, manufacturing and construction site staff, the heavy-duty test run was completed within 40 days after the main cable was crossed and the shortest record of domestic cable machine installation and commissioning was completed.