论文部分内容阅读
1大罐抽气装置的应用背景纯梁采油厂首站于1985年8月投产,是采油厂唯一的一座油气水泥综合处理站,目前,处理液量为750万吨/年。2004年站内安装了大罐抽气装置,但由于自动化技术和设备运行存在安全隐患,已于2006年停止使用,并拆除,造成站内储油罐和一次、二次沉降罐油气损耗严重,为充分利用能源,
Application Background of a Large-tank Extraction Unit The first station of the pure-beam production plant was put into operation in August 1985 and is the only one integrated processing station for oil-gas cement in the production plant. At present, the treatment volume is 7.5 million tons / year. In 2004, a large-tank extraction device was installed in the station. However, due to the potential safety hazard caused by automation technology and equipment operation, it was stopped in 2006 and dismantled. As a result, the depletion of oil and gas in the storage tanks and primary and secondary settling tanks in the station was serious and sufficient Use of energy,