“六五”GT试点企业济南第二机床厂自82年5月第一成组车间组建起,历时7年第二成组加工车间于去年动土新建,土建已于89年3月完成,4月15日第一单元设备已开始安装,于5月2日正式投产。 第二成组加工车间包括四个单元:小轴、大轴、板件及奇异件,建筑面积3000M~2,机床60台。继续采用一个单元投产,再组织一个另一单元搬迁的方法。这一车间全部建成后将加工全厂30%以上的零件,与原第一成
The “6th Five-Year” GT pilot company Jinan No. 2 Machine Tool Plant was established in May of the first group of workshops in May, and the second group of machining workshop lasted for 7 years. Last year, the civil engineering construction was completed in March of the year 89. The installation of the first unit on the 15th was started and it was put into production on May 2nd. The second group of processing workshops includes four units: small shafts, large shafts, plates and exotic parts, a building area of 3000 M~2, and 60 machine tools. Continue to use one unit to start production and then organize another unit to relocate. After this workshop is completed, it will process more than 30% of the parts of the whole plant, and the original first