大桥水库大(Ⅱ)型水利工程,由中国水利水电第五工程局投中二标(主、副坝及溢洪道)承包施工。该工程1993年9月开工,合同工期1997年3月完工。在施工中由于地质变化等问题,合同工期要推迟2年,预计1999年完工,因而需要调整合同费用。在费用调整中甲方、乙方、监理和设计4方,对调整费用的依据取得了共识,已对11个项目费用进行了调整。但对次要材料预算单价、人工费预算单位、主要材料预算单价取费、临建工程费用调整等尚未取得共识。
Large Bridge (Ⅱ) water conservancy project, by the Fifth Water Resources and Hydropower Engineering Bureau voted in two (main, auxiliary dam and spillway) contract construction. The project started in September 1993, the contract duration of March 1997 completed. In the construction due to geological changes and other issues, the contract duration to be postponed for two years, is expected to be completed in 1999, and therefore need to adjust the contract costs. In the adjustment of expenses, Party A, Party B, supervision and design 4 parties reached consensus on the basis for adjustment of expenses, and 11 project costs have been adjusted. However, no consensus has been reached on the budgetary unit price of budgetary materials, the budgetary unit of labor costs, the unit price of the main materials, the cost adjustment of construction projects, and so on.