论文部分内容阅读
第三年工程的規劃設計,是根據中央人民政府水利部第二次治淮工作會議决議‘中蓄洪排水結合治本,轉向多目標的發展’的精神製訂的,總的要求是繼續擴大蓄洪量,更進一步控制洪水,減輕內澇,興辦灌溉、航運等工程,使淮河水患巒爲永久的水利。第三年治淮工程總計要修建大型的山谷水庫六座,大的湖泊蓄洪工程一處,修建各種涵閘五十餘座,整理河道卅餘條。這些工程僅土工約需做一億八千多萬公方。
The planning and design of the third year project was formulated in accordance with the spirit of the “Resolution of the Second Huai River Working Conference of the Central Government on Water Conservancy”, which is based on the principle of flood storage and drainage combined with the principle of “multi-objective development”. The general requirement is to continue to expand the flood storage volume , To further control the floods, reduce waterlogging, set up irrigation, shipping and other projects, so that the Huai River flood Luan permanent water. In the third year of Huaihe River, a total of six large valley reservoirs, a large lake flood storage project and a total of more than 50 sluices will be built to finish the remaining sections of the river. Geotechnics of these projects only need to do more than 180 million public square.