飞龙岛大桥钢箱梁,采用了顶板、腹板、横隔板以及底板单元件工厂制造,工地现场3+1节段整体拼装;钢箱梁斜拉桥钢锚箱的高精度定位安装,采用了CAD空间三维坐标放样,工地现场以桥轴线和钢箱梁拼装胎模中心线为基准,采用全站仪进行空间定位,然后完成钢箱梁横断面悬臂挑梁安装。钢锚箱与钢箱梁外腹板系工地单面全熔透角焊缝,为了消除焊接残余应力,并制定了专项焊接消应措施。
Feilong Island Bridge steel box girder, the use of the roof, web, diaphragm and the floor of the single-component factory manufacturing, site 3 +1 overall assembly segment; steel box girder cable-stayed steel anchor box high-precision positioning installation The three-dimensional coordinate of the CAD space is set out. The site of the construction is centered on the axis of the bridge and the steel box girder. The total station is used for space positioning. Then the cantilever beam pick-up installation of the steel box girder is completed. In order to eliminate the welding residual stress and to develop special welding consumable measures, the single-side full penetration fillet weld of the steel anchor box and steel box girder outer web plate system site.