秦皇岛港煤码头一期工程(简称秦煤一期工程)是我国重点建设工程之一,也是我国自行设计施工和制造设备的一座现代化煤码头。该工程1975年底完成扩初设计,1977年完成修改扩初设计,1978年开始做施工图并开始施工,1983年4月1日前完成了单机试运转和空载联动试车,同年7月1日试投产。设计现代化煤码头,我院尚属第一次。由于技术复杂,工种交叉多,勘察设计工作量大,在设计工作中曾遇到不少困难和曲折。但在交通部和各级党委的正确领导下和秦皇岛港等单位的密切配合下,经过广大设计人员的团结协作,终于胜利地完成了任务。
Qinhuangdao Port Coal Terminal Phase I Project (Qin Coal Phase I Project) is one of the key construction projects in China and is also a modern coal terminal designed, constructed and manufactured by our country. The project was completed early 1975 by the end of the design, completed in 1977 to expand the early design, construction drawings began in 1978 and began construction, April 1, 1983 completed a single test run and no-load linkage test, the same year on July 1 test Put into production. The design of modern coal terminal, our hospital is the first time. Due to the complexity of technology, the large number of work types and the large workload of investigation and design, many difficulties and twists and turns have been encountered in the design work. However, under the correct leadership of the Ministry of Communications and party committees at all levels and with the cooperation of Qinhuangdao Port and other units, the task was finally successfully completed through the unity and cooperation of a large number of designers.