4月6日凌晨,为配合1号主变及三侧开关等设备由运行转检修,500千伏沙塘变电站值班员就忙开了,按照《变电设备停送电操作作业指导书》规定的标准、流程,共进行接地操作33组、相应保护操作18套;之后又协调各检修班组工作,确保了当天设备安全运行。
In the early hours of April 6, in order to cooperate with No. 1 main transformer, three-side switch and other equipment from operation to maintenance, the 500 KV Shatang substation on duty was busy. In accordance with the “Operation Guide for Transformer Equipment Shutdown Electricity Operation” Of the standards, processes, a total of 33 groups of grounding operation, the corresponding protection operation of 18 sets; and then coordinate the work of the maintenance team to ensure the safe operation of the day.