2014年8月5日22时,随着最后一车土被“清剿”出洞,城建集团承揽的东北热电供水工程一三五标最后一个大难题被成功攻破。项目执行经理郭明忠长吁了一口气,5个月的努力终于换回了胜利在望的利好。2014年一开春,水务工程部接到了一个急茬儿,位于北京市朝阳区的东北热电中心要在下半年完成正式运行工作,以保证2014年北京市东北部地区居民的冬季供热工
At 0:00 on August 5, 2014, the last big problem of the 115th TBP contracted by the Urban Construction Group was successfully solved as the last car was blown out of the hole. Guo Mingzhong, the project execution manager, took a deep breath and after five months of hard work finally recovered the good news of victory. In the spring of 2014, the Ministry of Water Resources Engineering received a stubborn stalemate. The Northeast Thermoelectric Center in Chaoyang District, Beijing, is scheduled to complete its formal operation in the second half of the year in order to ensure that the winter heating workers in the northeastern Beijing area in 2014