2011年,中国先进研究堆(CARR)工程在国防科工局、国家核安全局、中核集团公司及原子能院等上级部门的关怀指导下,CARR工程部组织相关单位抓紧时间,开展B阶段调试并处理各项技术问题,同期做好工程单项竣工验收工作。1CARR调试CARR的B阶段调试在去年完成大部分工作,本年度继续开展后续调试。1月11日在开堆提升功率时安全棒发生卡棒事件,CARR工程部立即组织相关单位对安全棒进行整治。设计修改由清
In 2011, CARR project under the guidance of the departments of National Defense Bureau, NNSA, CNNC and Atomic Energy Agency and other superior departments, CARR Engineering organized relevant units to seize the time to carry out B-phase commissioning Deal with various technical problems, do a good job single project completion and acceptance over the same period. 1CARR Commissioning CARR’s B-phase commissioning completed most of the work last year and continued to be followed up during the year. On January 11, when a stack of sticks was raised in the reactor to improve power, CARR Engineering immediately organized the relevant units to rectify the safety bars. Design changes by the clear