到2010年底,我国水电装机总容量达到213GW,约占技术可开发量的40%,很有发展余地。自主研制的以三峡工程为代表的700MW大型混流式水电机组达到世界先进水平,目前正在制造770MW溪洛渡和800MW向家坝机组,1000MW的机组也正在开发,将应用于白鹤滩水电站。为了实现能源结构调整和节能减排目标,到2030年水电装机还要有较大幅度的增长。为了抓住水电发展的机遇,不
By the end of 2010, China’s hydropower installed capacity has reached 213 GW, accounting for about 40% of the technically developable capacity. There is room for further development. The self-developed 700MW large-scale Francis turbine, represented by the Three Gorges Project, has reached the world advanced level. At present, 770MW Xiluodu and 800MW Xiangjiaba units are being manufactured and 1000MW units are under development and will be applied to Baihetan Hydropower Station. In order to achieve the goal of energy structure adjustment and energy conservation and emission reduction, the installed capacity of hydropower will have to increase substantially in 2030. In order to seize the opportunity of hydropower development, no