9月17日,随着168小时连续稳定运行试验的圆满完成,福清核电4号机组正式具备商业运行条件,标志着福清核电1~4号机组全面建成投产。福清核电4号机组于2012年11月17日正式开工,是福岛核事故后我国首批开工建设机组之一。4号机组商运投产,使福清核电总装机容量达到435.6万千瓦。福清核电正式进入“四驱时代”。自1号机组于2008年11月21日开工建设以
On Sept. 17, with the successful completion of the 168-hour continuous and steady operation test, Fuqing NPP Unit 4 formally had commercial operation conditions, marking the completion and commissioning of Fuqing NPP Units 1 to 4. Fuqing Nuclear Power Unit 4 officially started on November 17, 2012, which was one of the first units under construction in China since the Fukushima nuclear accident. Unit 4 put into operation, so that the total installed capacity of Fuqing nuclear power reached 4.356 million kilowatts. Fuqing nuclear officially entered the “four-wheel drive era.” Since Unit 1 on November 21, 2008 to start construction