首钢实行企业承包制后,自我积累,自我改造,自筹资金,陆续从国外引进了几项二手设备,其中之一是从比利时引进赛兰炼钢厂转炉设备和厂房钢结构。赛兰钢厂有两台210t氧气顶吹转炉。首钢除购买该套设备外,同时还购进了整个厂房钢结构及部分外围设备和厂房。为节约资金,结构和设备全由首钢派人到比利时拆运回国,总运输量达5万t,其中钢结构运输量占3.5万t(主厂钢结构设计重量约2.5万t)。
After Shougang implemented the enterprise contracting system, it self-accumulated, self-reformed, and self-financed, and gradually introduced several second-hand equipment from abroad. One of them was the introduction of the converter plant and steel structure of the Saillan Steel Plant from Belgium. The Sailan Steel Plant has two 210-ton oxygen top-blowing converters. In addition to purchasing the equipment, Shougang also purchased steel structures and some peripheral equipment and workshops throughout the plant. In order to save funds, the structure and equipment were sent by Shougang to Belgium to be shipped back to China. The total transportation volume reached 50,000 tons, of which steel structure transport volume accounted for 35,000 tons (main plant steel structure design weight was approximately 25,000 tons).