盾构的施工效率不仅直接关系到工程的施工进度,还与工程成本、质量和安全都有密切的联系。为了提高盾构施工效率,节约成本,确保盾构掘进过程中的质量安全。本文依托武汉地铁4号线泥水平衡盾构隧道工程实例,收集整理了越江段的工程概况和掘进参数数据,通过对盾构施工效率从不同角度的定义和计算,运用SPSS统计软件进行盾构掘进效率的参数影响因素分析,并讨论盾构掘进效率对各个参数变化的敏感程度,通过对比分析,研究盾构总施工效率低下的原因,找出影响盾构施工效率的关键因素并对施工过程中盾构掘进参数的控制提出合理建议。
Shield construction efficiency is not only directly related to the construction progress of the project, but also with the project cost, quality and safety are closely linked. In order to improve the efficiency of shield construction, save costs and ensure the quality and safety of shield tunneling. This article relies on the project example of mud-water balance shield tunnel of Wuhan Metro Line 4, collects and summarizes the project profiles and data of tunneling parameters of the Yuejiang section. Through the definition and calculation of shield construction efficiency from different angles, using SPSS statistical software for shield tunneling Efficiency of the parameters of the analysis of factors, and discuss the shield tunneling efficiency of the various parameters of the sensitivity of the change, through comparative analysis of the reasons for the overall shield shield low efficiency to identify the key factors that affect the efficiency of shield construction and construction process Shield tunneling parameters of the control proposed reasonable advice.