一是完成了466座小(2)型病险水库除险加固工程的初步设计审批工作,占全省1756座小(2)型病险水库的26.5%。二是加快推进小(1)型病险水库除险加固工作。250座小(1)型病险水库除险加固项目已经全部开工建设,累计完成投资9.74亿元,占总投资的85.9%,其中全部完工119座,竣工验收2座。三
First, the preliminary design approval of 466 small (2) type reservoirs for dangerous reservoirs was completed, accounting for 26.5% of 1,756 small (2) type reservoirs in the province. The second is to speed up the small (1) dangerous reservoir reinforcement work. The 250 small (1) type reservoirs for risk prevention and reinforcement project have all started to be constructed with a total investment of 974 million yuan, accounting for 85.9% of the total investment, of which 119 were completed and 2 were completed and accepted. three