豫联集团 2× 135MW技改工程循环流化床锅炉的烘炉采用安装临时烘炉机的热烟气烘炉法。当锅炉具备烘炉的必要条件 ,准备好了烘炉燃料、设备、仪器 ,安装好了烘炉设备后 ,可进行烘炉。烘炉分为烘炉机烘炉带酸洗的第 1阶段和锅炉整机启动前 ,利用主油枪对耐火材料进一步烘干的第 2阶段。实践证明 :采用热烟气烘炉机烘炉方法 ,其烘炉过程和烘炉温度易于监测、控制 ,最终达到烘炉要求。
Yulian Group 2 × 135MW technical transformation of circulating fluidized bed boiler oven installed temporary baking furnace hot flue gas oven method. When the boiler has the necessary conditions for the oven, ready for the oven fuel, equipment, equipment, oven equipment installed, can be oven. Ovens are divided into baking ovens with pickling stage 1 and the boiler before the start of the whole machine, the use of the main oil gun fire retardant further drying phase 2. Practice has proved that: using hot flue gas oven oven method, the oven process and oven temperature easy to monitor, control, and ultimately to the oven requirements.