论文部分内容阅读
结合杭州湾跨海大桥第四合同工程承台施工的工程实际,介绍深海承台钢套箱施工定位测量的常规的测量方法来进行承台定位放样,并结合竣工偏位测量采用GPS-RTK测量模式、牛腿销接的承重梁上弦杆在底板上的投影线利用全站仪反映到套箱的顶口并作标记和用三角高程来测承台标高的施工定位测量方法进行定测。
Combined with the engineering practice of the construction of the fourth contract cap of the Hangzhou Bay Sea-Crossing Bridge, the conventional measurement methods of the positioning and measuring of the steel cap box of the deep sea cap were introduced to locate the stake caps, and GPS-RTK was used in combination with the completion offset measurement Mode, the leg of the beam bearing beam beam on the floor projection line using the total station reflect the top of the box set and marked with a triangular elevation test platform elevation positioning method for measuring the positioning.