论文部分内容阅读
一机拖三泵不用过桥轴的具体安装方法如下:(一)第一种方法:(安装如图一)三个水泵和机器的旋转轴方向相同,把三个泵分别安装在高低不等的地基上,以使各泵皮带上下错开,便于皮带传动。水泵放置位置是:其中两泵可和动力机安装在同一立面上,另一泵下沉30—35度,第一泵要高于第三泵低于二泵,便于在中间交叉传动。(二)第二种方法,(安装如图二),三个水泵转向不一,反方向的一个放在第一泵的位置,挂带可采用“W 型”。(三)第三种方法:(安装如图三)用三条皮带传动。三个水泵和动力安装在同一个地平面上,旋转方向不同。
A machine towing three pumps without bridge shaft specific installation methods are as follows: (A) The first method: (installation shown in Figure 1) The three pumps and machine rotation axis in the same direction, the three pumps were installed at different levels The foundation, so that the pump belt up and down staggered, easy belt drive. Pump placement is: Two of the pumps can be installed on the same plane with the power machine, the other pump sinks 30-35 degrees, the first pump is higher than the third pump is lower than two pumps, easy to cross drive in the middle. (B) The second method, (installed as shown in Figure 2), the three pumps are not the same, one in the opposite direction on the first pump position, the strap can be used “W-type.” (C) The third method: (installation shown in Figure III) with three belt drive. Three pumps and power installed in the same ground plane, different directions of rotation.