论文部分内容阅读
白莲河水库位于鄂东大别山南浠水河上,1960年完成,控制流域面积1800平方公里,库容11亿立米,是一个综合利用工程。在毛主席无产阶级革命路线指引下,该工程综合效益逐年增大。他们的经验主要有:(1)狠抓工程管理。由于职工觉悟提高,对土坝的观测十分重视,确保了大坝安全。同时还注意了大坝检修工作,如副坝粘土心墙比设计高程低0.96米,影响水库拦洪
The Bailianhe Reservoir is located in the south Xishui River of the Dabie Mountain in eastern Hubei Province and was completed in 1960 with a control basin area of 1,800 square kilometers and a storage capacity of 1.1 billion cubic meters. It is a comprehensive utilization project. Under Chairman Mao’s proletarian revolutionary line, the overall efficiency of the project has been increasing year by year. Their experience mainly includes: (1) pay close attention to project management. Due to the increased awareness of workers, great attention was paid to earth dam observation to ensure dam safety. At the same time also pay attention to the dam overhaul work, such as vice dam clay wall than the design elevation of 0.96 meters, affecting the reservoir flood control