最高人民法院《关于审理建设工程施工合同纠纷案件适用法律问题的解释》第20条规定:“当事人约定,发包人收到竣工结算文件后,在约定期限内不予答复,视为认可竣工结算文件的,按照约定处理。承包人请求按照竣工结算文件结算工程价款的,应予支持。”最高院的这一司法解释规定,无疑是解决目前建筑市场存在的,建设工程发包人违约逾期不结算工程价款的一把尚方宝剑。然而,要正确地适用上述规定,实现“以送审价为准”的目的,在实务操作中还有着其特殊的条件和要求。
Article 20 of the Interpretation of the Supreme Court on the Application of Legal Issues in the Trial of Disputes over Construction Contracts for Construction Projects stipulates: “Upon agreement by the parties, the Employer shall not reply within the agreed time limit after receiving the completion settlement documents, Documents, in accordance with the agreement.When the contractor request settlement of the project price in accordance with the completion settlement documents, should be supported. ”The Supreme Court of this judicial interpretation of the provisions is undoubtedly to solve the current construction market exists, the construction contractor default overdue Settlement project price is still a sword. However, the correct application of the above provisions and the realization of the objective of submitting the trial price shall have special conditions and requirements in the practical operation.