三峡大坝和电站厂房二期工程土建与安装合同 (合同编号 :TGP CIV -4 -I&IIB)合同金额 3 7.71亿元 ,合同工期 10a( 1997~ 2 0 0 7年 )。投资金额大、分项工程多、工期长、影响工程投资的不可预见因素多 ,是I&IIB标合同支付管理的特点。I&IIB标合同支付管理坚持以“承建合同为依据 ,单元工程为基础 ,工程质量为保证 ,量测核实为手段”的原则 ,有效控制了工程价款的支付 ,促进工程建设的顺利进展 ,确保投资控制目标的实现 ,同时为以后的合同支付管理工作提供了一些可借鉴的经验。
Construction contract for the construction and installation of the second phase of the Three Gorges Dam and power station building (Contract No. TGP CIV -4 -I & IIB) amounted to RMB3771 million with a contractual period of 10a (1997-2707). There are many unforeseen factors such as large amount of investment, sub-project, long construction period and impact on project investment, which are the characteristics of I & IIB contract payment management. I & IIB Contract Payment Management Adhere to the principle of “contract based on the basis of unit construction, engineering quality assurance, measurement and verification as a means” to effectively control the payment of the project price and promote the smooth progress of construction to ensure that investment control The realization of the goal, at the same time, provides some lessons for the contract payment management in the future.