中国长江三峡集团公司于2004年3月进驻向家坝开始筹建,2006年11月正式开工,2008年12月成功实施截流。至2012年10月,向家坝二期大坝浇至高程363m~384m,平均高程372m(坝顶高程384m),满足了水库蓄水要求。2012年10月10日,向家坝水电站开始下闸蓄水,10月16日蓄至水位354m,达到水库初期蓄水目标水位,满足了首批机组发电要求,2012年11月5日,向家坝水电站首台单机组(7号机)正式投产发电。
China Three Gorges Corporation in March 2004 stationed in Xiangjiaba began construction, in November 2006 formally started in December 2008, the successful implementation of closure. As of October 2012, the dam of Xiangjiaba Phase II was poured to an elevation of 363m ~ 384m with an average elevation of 372m (crest elevation of 384m), meeting the reservoir water requirement. On October 10, 2012, the Xiangjiaba Hydropower Station started to shut down for water storage and reached a water level of 354m on October 16, reaching the initial water storage target level of the reservoir and meeting the power generation requirements of the first batch of units. On November 5, 2012, Jiaba Hydropower Station’s first single unit (No. 7) was officially put into operation.