传统的地下管道施工是“挖槽埋管法”。穿越道路或河流时,若采用钢开施工使道路的质量变差,寿命变短,污染环境;若采用钢顶施工则成本较高,而且地下管道被挖断的事故时有发生,造成不应有的经济损失。以大庆油田采油八厂第二油矿宋II-41#配水间—2#配水间管道敷设为例,该工程施工过程中使用了非开挖管道定向穿越技术,取得了一定的效果。将非开挖管道定向穿越技术与传统开挖技术进行对比,非开挖法施工会在一定程度上缩短施工工期,降低环境影响,提高工作效率。
The traditional construction of underground pipe is “digging buried pipe ”. When crossing the road or river, if steel construction is used to make the quality of the road worse, the service life will be shortened and the environment will be polluted. If the steel roof construction is used, the cost will be high, and underground pipes will be cut accidentally. Some economic loss. Take Daqing Oilfield 8th Oil Production Plant No. 2 Oil Mine Song II-41 # water distribution -2 # distribution pipe laying as an example, the project construction process using non-digging pipe directional through technology, and achieved some results. The non-digging pipe directional through technology and traditional excavation technology comparison, trenchless construction will to some extent shorten the construction period, reduce environmental impact and improve work efficiency.