论文部分内容阅读
甬台温铁路是我国铁路规划的“四横四纵”线路之一,设计时速200 km/h,远期预留250 km/h。施工地处东南沿海地区,地质地貌复杂多变,地基处理尤为重要。台州站站前工程大区域复杂软土地基部分区段采用直径500 mm的预应力管桩处理,施工区域在长1018 m、宽62 m的范围,共需施工预应力管桩578731延米,桩长37~45 m,桩间距2.4 m。施工区域周边乡村居多。
The Ningbo-Taizhou-Wenzhou Railway is one of the “four horizontal and four vertical” lines of China’s railway planning with a design speed of 200 km / h and a forward reservation of 250 km / h. Construction is located in the southeast coastal areas, complex and changeable geological landscape, foundation treatment is particularly important. The section of complex soft soil foundation in the large area of Taizhou station before engineering is treated with prestressed pipe piles with a diameter of 500 mm. The construction area is 1018 m long and 62 m wide. A total of 578,731 pre-stressed pipe piles are required to be extended, Length 37 ~ 45 m, pile spacing 2.4 m. The majority of rural villages around the construction area.