河南省郑州市污水处理厂位于郑州市东郊,日处理城市生活污水80万t。其进厂污水干管西起郑汴路,东到污水处理厂厂区,全长8570m。由于管道沿线地层主要由粉土、粉质黏土和粉砂组成,地下水位-0.7~-1.0m。污水进厂干管沿线穿过5条规划道路,横穿两条铁路专用线,30个渔塘,5个较大的村庄和1座桥梁。采用常规开挖埋管,很难操作,经过综合考虑,决定采取封闭式土压平衡顶管施工的方法。其工艺主要由沉井和顶进两部分组成:
Zhengzhou City, Henan Province, sewage treatment plant is located in the eastern suburbs of Zhengzhou City, Japan’s urban sewage treatment 800,000 t. The sewage pipe into the plant west from Cheng Kau Road, east to the sewage treatment plant, a total length of 8570m. As the formation along the pipeline is mainly composed of silt, silty clay and silt, groundwater level -0.7 ~ -1.0m. Sewage into the plant trunk along the five planned roads, crossing two railway lines, 30 fishing ponds, 5 larger villages and 1 bridge. Using conventional excavation pipe, it is difficult to operate, after comprehensive consideration, decided to adopt a closed earth pressure balanced pipe jacking method. The process consists of caisson and top two parts: