科特迪瓦当地时间4月20日9时40分,由成都院承担设计及机电设备成套供货的苏布雷项目主电站2号发电机转子,一次性吊装成功。苏布雷项目主电站发电机转子直径10.62 m,重约350 t,由2×200 t桥机起吊,全过程历时40 min。主电站2号发电机转子吊装成功,不仅为首台机如期发电提供了条件,也为后续机组按计划发电奠定了坚实基础。苏布雷水电站位于西非科特迪瓦境内萨桑德拉河上纳瓦瀑布处,主电站装设3台90 MW混流式机组,微型电站装设1台
At 20:40 local time on April 20, at 9:40 on April 20, the Chengdu No.2 Electric Vehicle Co., Ltd. took charge of the design and complete sets of mechanical and electrical equipment to supply the No. 2 generator rotor of Subrai Project, which was successfully lifted at one time. The main rotor of Subrai project has a rotor diameter of 10.62 m and a weight of about 350 t. It is hoisted by a 2 × 200 t bridge crane and the entire process lasted 40 minutes. The successful installation of No.2 generator rotor of the main power station not only provided conditions for the first unit to generate electricity on schedule, but also laid a solid foundation for subsequent units to generate power according to plans. The Suprai Hydropower Station is located at Nahuat Falls on the Sassandra River in Cote d’Ivoire, West Africa. Three 90 MW Francis units are installed at the main power station and one at the micro power station