论文部分内容阅读
建筑施工中,首先遇到的就是场地整平问题。这涉及到土石方工程量的计算。如果能使土石方挖填平衡,可节省工时、人力等,提高效率,减少开支。所以,土石方工程量的计算是重要的。现将土方施工的方格网法和横断面计算法介绍如下:一、方格网法方格网计算法应用较广泛,计
In the construction process, the first problem encountered is the leveling of the site. This involves the calculation of earthwork volume. If earthwork can be dug and balanced, man-hours and manpower can be saved, efficiency can be improved, and expenditure can be reduced. Therefore, the calculation of earthwork volume is important. The square grid method and cross-section calculation method for earthwork construction are now described as follows: 1. Grid grid method The grid grid calculation method is widely used.