本文介绍了第一汽车制造厂在主动圆柱齿轮自动线改造工程中采用网络计划进行管理的情况。经过6个月的实践;应用这种方法获得了成功,使整个改造工程完成时间提前半个月。文中附有该工程的网络图。在网络图上可明显看出整个工程所包括的工作项目及其相互关系。根据网络图通过计算得出日程计划表。网络计划可解决以往由于计划不周而发生的问题。
This article describes the first automobile factory in the initiative of automatic transformation of cylindrical gear automatic network project management situation. After 6 months of practice, the successful application of this method has resulted in the completion of the entire renovation project by half a month. Text attached to the project network map. In the network diagram can clearly see the entire project includes the work items and their interrelationships. Calculate the schedule according to the network diagram. Network plan to solve the past because of poor planning problems.