高层建筑主体结构标准层施工过程具有循环施工的特点,采用传统计划编制方法具有一定的局限性。文章将ABC仿真系统应用到高层建筑标准层施工仿真中来,并将CPM网络计划技术的优点融入到ABC仿真建模中,使模型更加符合实际施工过程。通过仿真分析,可以得到标准层施工工期及各项资源利用率;通过敏感性分析,可以得到最优的机械配置参数。工程实例表明,采用这种建模方法模拟标准层施工过程是有效的。
The main floor of the main structure of the standard construction process has the characteristics of circular construction, the use of traditional planning methods have some limitations. The article applies the ABC simulation system to the simulation of the standard building construction of high-rise building, and integrates the advantages of CPM network planning technology into the ABC simulation modeling to make the model more in line with the actual construction process. Through the simulation analysis, we can get the standard construction period and the utilization rate of various resources; through the sensitivity analysis, the optimal mechanical configuration parameters can be obtained. The engineering examples show that it is effective to use this modeling method to simulate the standard layer construction process.