论文部分内容阅读
近些年来,引洪淤灌工程在內蒙古自治区有了很大发展。这是我区水利事业上的一件大事。为了总結群众的技术經驗,我們曾在烏兰察布盟的兴和县、涼城县、土默特旗和呼和浩特市郊区进行了一个多月的調查。現将这些材料整理如下,供作研究参考。一、渠首枢紐工程本地区的洪水特点是,峯高量少,陡漲陡落,变幅大,含沙量大,推移质多。因而渠首工程必須滿足以下要求,才能保质保量地引取洪水:(1)有較大的泄洪能力,保证泄洪安全;(2)有良好的导流性
In recent years, flood diversion project in Inner Mongolia has made great progress. This is a major event in our district water conservancy project. In order to summarize the technological experience of the masses, we conducted a multi-month investigation in Xinghe County, Liangcheng County, Tumote Banner and the outskirts of Hohhot in Wulanchabu League. These materials are now organized as follows for reference. First, the head of the hub project The floods in the region is characterized by less peak height, steep rise and fall, large amplitude, large amount of sediment, quality and more. Therefore, the headrace project must meet the following requirements to be able to introduce floods with quality and quantity: (1) greater flood discharge capacity to ensure flood discharge safety; (2) good diversion