上海浦东国际机场T1航站楼流程改造工程中,为满足既有连廊上部结构加建后的承载力要求,对既有连廊首层基础结构进行加固。既有连廊首层净空高度仅约为4m,加固施工的全过程中既有连廊二层、三层均处于正常运营状态,且加固设计节点复杂,给围护结构施工、增设混凝土灌注桩以及首层结构加固带来了极大的困难。经过现场实测并结合设计图纸反复研究,采取改进施工机械、调整压顶梁结构设计、优化加固节点施工流程等措施,解决了不停航条件下既有连廊基础结构加固施工难题,加快了工程进度,节约了工程费用,确保了基础结构加固过程中航站楼不停航运营的安全。
Shanghai Pudong International Airport T1 Terminal Process Improvement Project, in order to meet the existing structure of the upper corridor after the construction of additional capacity requirements, the existing corridor on the ground floor of the first reinforcement. The clearance height of the existing corridor at the first floor is only about 4m. In the whole process of reinforcement construction, both the second floor and the third floor of the corridor are in normal operation, and the reinforced design nodes are complex, so as to construct the enclosure structure and add concrete filling piles As well as the structural reinforcement of the first floor has brought great difficulties. After the field test and the repeated research on the design drawings, the measures such as improving the construction machinery, adjusting the structural design of the pressure roof beam and optimizing the construction process of the reinforcement joints are taken to solve the difficult problems of the existing corridor foundation structure under non-stop navigation conditions, speeding up the construction progress, The project cost is saved, which ensures the safety of the non-stop operation of the terminal building during the process of reinforcing the infrastructures.