根据施工技术规范,库尔普赛水电站大坝混凝土浇筑层高为1米。浇筑块的平面尺寸由坝块长和坝剖面宽所确定。中间的两个坝块的长度为19.5米,其余坝块长30米。剖面宽度的变化为,高程30米处宽58米,高程65米处宽37米。当混凝土浇到高程68米后,大坝下游面设了键槽,以满足在1981年形成机组启动水头的需要。大坝平均上升高度为2.7米/月,并根据季节性的变化,大坝上升高度为2~3米/月。相邻层的混凝土浇筑间歇时间为7~12昼夜。
According to the construction specifications, the height of concrete pouring of the dam of Kurpur race station is 1 meter. The plan dimensions of the pouring block are determined by the length of the dam and the width of the dam. The length of the two dam blocks in the middle is 19.5 meters and the remaining dam blocks are 30 meters long. The change of section width is that the elevation is 30 meters, the width is 58 meters and the elevation is 65 meters and the width is 37 meters. When the concrete was poured to an elevation of 68 meters, a keyway was arranged on the downstream of the dam to meet the need of starting the head of the unit in 1981. The average height of the dam rises 2.7 meters / month, and according to the seasonal changes, the height of the dam rises to 2-3 meters / month. Adjacent layer of concrete pouring intermittent time of 7 to 12 days and nights.