山岭隧道穿越冲沟段施工风险分析与控制措施

来源 :地下空间与工程学报 | 被引量 : 0次 | 上传用户:hhuzw
下载到本地 , 更方便阅读
声明 : 本文档内容版权归属内容提供方 , 如果您对本文有版权争议 , 可与客服联系进行内容授权或下架
论文部分内容阅读
以湖南省炎汝高速公路梅子山隧道为依托,根据冲沟段的地形地质条件,通过数值模拟研究浅埋偏压和拱部出露两种情况的施工力学行为,辨识施工中存在的不利因素,进行施工风险分析,提出隧道穿越冲沟段施工存在塌方、大变形、渗漏水、边仰坡失稳等风险事件,并有针对性地提出风险控制措施。结合现场施工与监测情况,讨论现场实施效果,洞内外变形正常,未发生突发事故,风险控制措施切实可行,可供同类型山岭隧道穿越冲沟段施工提供参考。 Based on the topographic and geological conditions in the gully section of the Autonomous Region on the Meishan Tunnel of Yan - Ru Expressway in Hunan Province, the construction mechanics behaviors of shallow bias and arch exposed are studied by numerical simulation to identify the unfavorable factors in construction , The risk analysis of the construction was carried out, and some risk events such as landslide, big deformation, seepage water and instability of the slope on the slope were proposed during construction of the tunnel across the gully. Risk control measures were put forward in a targeted manner. Combined with the site construction and monitoring, the site implementation effect is discussed, the deformation inside and outside the cave is normal, no unexpected accident occurs, and the risk control measures are feasible, which can provide reference for the same type of mountain tunnel construction across the gully.
其他文献
塔里木H油田整体采用水平井开发,全部采用机采完井,受井况限制,动态监测风险和难度很大。攻关形成了一套具有塔里木油田特色的产层参数测井解释方法,实现了超深、高温、高矿化度
实施卓越计划,培养创新能力强、适应经济社会发展需要的应用性复合型经管类本科人才是应国家之需、适时代之求,而组织实施好大学生到企业实习是应用性人才培养的关键环节。本文
风荷载是高、大、细、长等柔性结构的重要设计荷载,有时甚至起到决定性作用,抗风设计是工程结构中的重要课题。风荷载和结构的设计参数具有明显的随机不确定性,因此从概率角度研
<正>《宁夏工程技术》是国家科学技术部和新闻出版总署于2001年12月4日正式批准创办的公开发行的科技期刊;由宁夏大学主办,宁夏回族自治区教育厅主管。办刊宗旨:(1)及时向社