我厂生产的 HZWA 型金属支柱,原来焊接活柱这道工序是由自动焊机来完成的。焊接前,先由两名铆工对焊,焊工再进行焊接,每台焊机要配备四、五名焊工,每个班就要占用劳动力十几人。而对焊时,二十多公斤的活柱要搬上搬下,卡紧翻身,全由人工进行,故劳动强度大,质量也不能保证。而利用 EK1000型自动焊机,焊丝要经常更换,焊接效率低,不能适应生产新形势的需要。
I plant the production of HZWA-type metal pillars, the original welding column this process is done by the automatic welding machine. Before welding, the first by two riveting welds, welders and then welding, each welder to be equipped with four or five welders, each class will take up more than a dozen workforce. The butt welding, more than 20 kilograms of pillars to be moved down, chucking turn over, all by hand, it is labor-intensive, quality can not be guaranteed. The use of EK1000 automatic welding machine, welding wire to be replaced frequently, welding efficiency is low, can not meet the needs of the new situation of production.