论文部分内容阅读
一、概述牛路岭水电站是开发海南岛的重点工程之一,大坝采用直线形空腹式重力坝,最大坝高为90.5m,坝顶长341.2m,位于海南岛万泉河支流上,电站装4台机组,总装机容量80MW,溢洪道设置在河床中央坝段,有7扇8.5m×15.65m的弧形闸门。
I. Introduction Niuluiling Hydropower Station is one of the key projects for developing Hainan Island. The dam adopts linear fast-acting gravity dam with a maximum dam height of 90.5m and a crest length of 341.2m. It is located on the tributaries of Wanquan River in Hainan Island. The station Installed 4 units, with a total installed capacity of 80MW, spillway set in the central dam section, there are seven 7.5m × 15.65m of the arc gate.