论文部分内容阅读
以叶尔羌河喀群引水枢纽除险加固工程为实例,探讨喀群引水枢纽除险加固的施工方法。本工程分为一期和二期工程,文中简要介绍了工程概况,其次介绍了叶尔羌河附近的水文气象和工程地质,最后着重阐述了部分除险加固施工方法。通过本文的阐述,为以后的除险加固工程提供理论基础。
Taking the Yalqiang River Cascade Water Diversion Project reinforcement project as an example, the construction method of the Qiongqu diversion project reinforcement project is discussed. This project is divided into the first phase and the second phase. The article briefly introduces the general situation of the project, secondly introduces the hydrological meteorology and engineering geology near the Yarkant River, and finally elaborates some construction methods of reinforcement. Through the elaboration of this article, it provides the theoretical basis for the future reinforcement project.