论文部分内容阅读
鋼筋混凝土装配式水池是新結构、新技术,质量要求較高的建筑物。修建在××x站40m高的山坡上。在搗制的混凝土基础上安裝16块壁板(寬1.2m×长3.6m)和以中柱支撑的8块盖板(2.5m×2.75m)等鋼筋混凝土預制构件拼装组成,最重构件达1.56t。我处接受这一任务后,深入現場勘測,组織干部、技术人員、老工人在討論构件預制、运輸、吊装、接縫等施工方案时都有不同的看法。在构件的制做上,研究二种方案,施工中又都有困难。一个是在現地預制,势必要迁到山地不平,場地窄預,无水源无电源等施工困难,另一个方案是在錦州預制厂預制,虽然施工条件較好,但构件沉重,往40m的高山上运輸也是一大关。因此,在部分人員中产生了三怕思想:一怕、沒有完整成套的机械設备吊装不了。二怕、水池滿水环筋受张壁板外移。三怕、接縫漏水交不了工。有的人說:裝配式水池比搗制水池不仅不經济而且质量也沒有把握。針对
The reinforced concrete assembly pool is a new structure, new technology, and a building with high quality requirements. Built on a 40m-high hillside at Xxx. 16 pieces of siding (1.2m wide and 3.6m long) and 8 reinforced concrete prefabricated blocks (2.5m x 2.75m) supported by the middle column are assembled on the concrete foundation for ramming. Up to 1.56t. After accepting this task, our department conducted in-depth surveys on the site and organized cadres, technicians, and old workers to have different opinions when discussing construction plans for component prefabrication, transportation, hoisting, and jointing. In the manufacture of the components, the two schemes were studied and there were difficulties in the construction. One is prefabricated in the existing site and is bound to move to uneven mountains, narrow construction sites, and construction difficulties such as no water source and no power supply. Another project is to prefabricate the prefabricated factory in Jinzhou. Although the construction conditions are good, the components are heavy and the mountains are 40 meters high. Transport is also a big one. Therefore, there are three fears of thought among some people: one is afraid that there is no complete set of mechanical equipment that cannot be mounted. Second, fear that the pool full of water ring ribs by the siding board outside. Three fears, joints leaking can’t pay for work. Some people say that a fabricated pool is not only less economical than a tanning pool and its quality is uncertain. against