1 工程概况禹州电厂一期自流式取水站工程位于禹州市白沙水库东岸左坝肩下游,合同总造价912万元。主要工程项目包括:6000m~3蓄水池两座、平流式沉淀池两座、取水头部、节制闸、排泥阀门井、阀门切换井、流量计间、站内外引排水管道、配电控制室、职工宿舍及其它附属建筑物等。合同要求质量等级为优良。合同工期4个半月。该工程工期紧、施工难度大、质量要求高,并充分贯彻应用ISO9002质量体系。2 文件和资料控制程序的运用为保证工程紧张有序地进行,项目部编制了一系列质量保
1 Project Overview Yuzhou Power Plant a gravity flow water intake project is located in Yuzhou Baisha reservoir on the left bank of the dam downstream, the total contract cost 9120000 yuan. Major projects include: two 6000m ~ 3 reservoirs, two advection sedimentation tanks, water head, control gates, mud valve wells, valve switching wells, between the flowmeter, drainage channels inside and outside the station, distribution control Rooms, staff quarters and other ancillary buildings. The contract requires a good quality grade. Contract duration of four and a half months. The project duration tight, difficult construction, high quality requirements, and fully implement the ISO9002 quality system. 2 documents and data control program to ensure that the project was conducted in an orderly manner, the project department has prepared a series of quality assurance