青岛炼化是经国家发改委批准、跨“十五”“十一五”计划的中国石化战略项目,也是21世纪中国第一座千万吨级炼油项目。自2007年6月全面进入设备安装阶段,12月大件安装基本结束,前后大约经历了半年的时间。青岛大炼油工程共有80t以上的大型设备97台,计172件,吊装总重量19 952t。其中,质量最大的设备是再生器重达1 090t,单件吊装质量最大的设备是加氢处理反应器,达660 t,最高的设备是连续重整反应器,达77 m。上述这些大型设备由中石化十公司以“吊装一体化”的方式承包施工,其他设备由承包商自行负责安装。在施工现场主要采用了特雷克斯-德马格CC8800、
Qingdao Petrochemical is approved by the National Development and Reform Commission, across the “fifteen ” “Eleventh Five-Year ” plan of Sinopec strategic project, is also the 21st century China’s first 10 million-ton refinery project. Since June 2007 fully entered the stage of equipment installation, large-scale installation in December basically ended, after about half a year’s time. Qingdao large oil refining project a total of more than 80t large-scale equipment 97 units, accounting for 172, lifting the total weight of 19 952t. Among them, the highest quality equipment is the regenerator weighed 1 090t. The single-piece lifting equipment with the highest quality is a hydroprocessing reactor up to 660 t. The highest equipment is a continuous reforming reactor up to 77 m. These large-scale equipment by the Sinopec 10 companies to “hoisting” the way contractor construction, other equipment by the contractor is responsible for the installation. Mainly used in the construction site Terex Demag CC8800,