兴隆庄选煤厂设计年入选原煤300万吨,它是上海宝山钢厂的配套项目之一。该选煤厂是由山东省煤炭设计院与美国罗伯茨—谢菲尔公司联合设计,由兖州煤炭建设公司第37工程处承担建筑和安装,由兖州煤炭建设公司第2工程处承担原煤仓、精中煤仓基础灌注桩和铁路站线的施工任务。主厂房于1982年1月16日开工,1984年9月28日全系统开始带煤试生产,1984年12月31日内部移交
Xinglongzhuang Coal Preparation Plant selected in the design of coal 3 million tons, it is Shanghai Baoshan Iron and Steel plant one of the supporting projects. The coal preparation plant by the Shandong Provincial Coal Design Institute and the United States Roberts - Sheffield company jointly designed by the Yanzhou Coal Construction Company No. 37 Engineering Office to undertake the construction and installation by the Yanzhou Coal Construction Company No. 2 Engineering Department to undertake the original coal warehouse, refined The Construction Task of Basement Pile and Railway Station in Coal Bunker. The main plant was started on January 16, 1982, September 28, 1984 the whole system began with coal production test, December 31, 1984 internal transfer