挡土墙施工通常是先基础,后上部,自下而上地进行。文章以江苏省水情调度中心大楼工程的道路边坡维护问题为例,介绍一种自上而下的挡土墙施工方法──“逆作法”。
Retaining wall construction is usually the first foundation, after the upper part, from bottom to top. Taking the maintenance of road slopes in Jiangsu Provincial Hydrological Dispatch Center building as an example, this paper introduces a top-down retaining wall construction method called “reverse method”.