本钢炼铁厂5号高炉1972年建成,2001年扩容大修,高炉在炉腹、炉腰以及炉身下部的B2和S1两段铜冷却壁是引进PW公司设计国内首次采用超长壁体。B2和S1两段铜冷却壁每段46块,每段冷却壁共有184根水管。由于冷却壁过长,受热应力作用容易变形,B2和S1两段铜冷却壁水管出现漏水。通过本次改造将二段冷却壁改为四段铸铜冷却壁,为尽早恢复炉况,利用中修进行改造,为保证工期,在中修过程中采用了科学管理和多项创新技术,使5号高炉提前投产,并短期内达产,创造了可观的经济效益。
Bengang Iron and Steel Works No. 5 blast furnace built in 1972, 2001, expansion and overhaul, blast furnace in the belly, furnace waist and lower part of the B2 and S1 two sections of the copper stave is the introduction of PW design for the first time using ultra-long wall. B2 and S1 two sections of copper staves each 46, each stave a total of 184 water pipes. As the cooling wall is too long, easy to deform by the role of thermal stress, B2 and S1 two sections of copper cooling pipe water leakage. Through this transformation, the second section of the cooling wall will be replaced by four sections of copper cooling staves, as early as possible to restore the furnace conditions, the use of repair in the transformation, in order to ensure the duration of the repair process in the use of scientific management and a number of innovative technologies to enable 5 blast furnace put into operation ahead of schedule, and short-term production, creating considerable economic benefits.