山西古交屯兰矿井是国家计委、财政部、中国人民建设银行、物资部共同批准的以设计为主体进行工程建设全过程总承包的基建管理体制改革首批试点项目之一。1987年5月,国家计委和原煤炭部通过招标确定由江苏省煤矿设计院组建江苏煤炭工程公司对该矿井进行总承包。由于征地、供电等困难较大,工程推至1988年10月才破土动工。经过半年施工准备,1989年5月正式开工。总结20个月的承包试点工作,我们的体会是:以设计为主体进行工程建设总承包,是国家控制基建投资,提高投资效益的有效
Shanxi Gujiao Tunlan Mine is one of the first pilot projects of the reform of infrastructure management system under the general contracting of projects throughout the entire construction process with the approval of the State Planning Commission, the Ministry of Finance, the People’s Construction Bank of China and the Materials Department. In May 1987, the State Development Planning Commission and the former Ministry of Coal determined by bidding that the Jiangsu Coal Mining Design Institute set up the Jiangsu Coal Engineering Company to contract the mine. Due to the difficulties such as land acquisition and power supply, the project was pushed to ground until October 1988. After six months of construction preparation, in May 1989 formally started. To summarize the 20-month contractual pilot work, our experience is that the general contracting of construction projects based on design is the result of the state’s control of infrastructure investment and the enhancement of investment returns