以深溪沟围堰水库为调节水库,论证了瀑布沟水库初期蓄水期间,在50%、80%、90%来水保证率情况下,深溪沟水库提前蓄水、瀑布沟水库下闸蓄水、深溪沟水库临时供水等过程的具体实施方案,提出以80%来水保证率作为设计保证率,并讨论了瀑布沟水库实施蓄水时,在上游来流量为960m3/s,尼日河来流量为64m3/s的情况下,两库的运行过程。
Taking Shenxigou cofferdam as a regulation reservoir, it is demonstrated that during the initial storage period of Pubugou Reservoir, under conditions of 50%, 80% and 90% of guaranteed water rates, Shenxigou reservoir pre-impounding water and Pubugou reservoir impounding Water and Shenxigou reservoir temporary water supply and so on, put forward a guarantee rate of 80% water as a design guarantee rate, and discussed the Pubugou reservoir implementation of water storage, upstream flow to 960m3 / s, Niger River flow to 64m3 / s case, the two banks of the operation process.