路基的压实质量是高填方路基工后沉降控制的主要手段之一,因此,如何提高路基的压实质量成为高填方路基施工的关键。针对某湿陷性黄土高填方公路路基进行了填筑工艺试验,压实施工采用压路机碾压、冲击碾碾压及强夯实,对碾压机械、填料含水率、不同压实机械的单层压实厚度等参数进行了试验分析。结果表明,考虑重锤夯实的需要,现场施工时填料含水量低于最优含水量约5%;压路机碾压的经济合理虚铺厚度约为40cm;当每填筑三层进行一次冲击碾压并在约5 m处进行一次强夯时,填土的压实度得到了很大提高,并有效地减少了工后沉降。
The compaction quality of roadbed is one of the main means of post-construction settlement control of high-fill roadbed. Therefore, how to improve the compaction quality of roadbed becomes the key to the construction of high-fill subgrade. For a collapsible loess high-fill highway embankment filling test, compaction construction using roller compaction, impact milling and compaction, the compaction of rolling machinery, packing moisture content, different compaction machinery of the single layer Compaction thickness and other parameters were tested. The results show that, considering the need of heavy rammed compaction, the water content of filler in construction site is less than about 5% of the optimal water content; the economically reasonable virtual paving thickness of road roller compaction is about 40cm; At a dynamic compaction of about 5 m, the degree of compaction of the fill is greatly increased and post-construction settlement is effectively reduced.